Murra Warra II Wind Farm, Victoria

Murra Warra II Wind Farm is located in North Western Victoria, 25km north of Horsham. The wind project has a capacity of 209MW and is comprised of 38 turbines. Murra Warra II Wind Farm generates enough electricity to power more than 175,000 homes and prevent around 640,000 tonnes of carbon emissions annually.

Key Project Info

Wind Turbines

38

Maximum Capacity

209MW

Annual Output

809GWh

PPA Partners

Snowy Hydro

175k
640k
130
$40m

Project Timeline

Step 1/13

Project identification and site selection

Identification and site selection is based on an analysis of opportunities and constraints, including (but not limited to): distance to the electricity grid, wind resource, potential impacts on ecology and population density of the surrounding community. Our team then undertake a number of site visits and consultation with key stakeholders and local community.

Current Stage
Projeect Feasibility2

Step 2/13

Project feasibility and community engagement

Site-specific investigations are undertaken to assess the impacts and opportunities of the project and feedback is sought from the local community.

Current Stage
160m Mast

Step 3/13

Planning Permit and EES

Prior to applying for a planning permit, a referral is made to the Victorian Minister for Planning to determine if an Environmental Effects Statement (EES) is required. If required, the EES preparation is done in parallel with the planning application. If not required, a planning application is submitted, addressing environmental and social impacts, which is also assessed by the Minister for Planning.

Current Stage
Pexels pixabay 357514

Step 4/13

Public exhibition

When the Minister is satisfied that the planning application is suitable it is released for public comment. During this time the public can make written submissions.

Current Stage
IMG 80711

Step 5/13

Assessment and development consent

The Minister for Planning may appoint a panel to evaluate the project. Hearings take place and project documents are assessed by relevant government authorities. The panel reports to the Minister for Planning with recommendations. If the project is approved, a planning permit is granted with project-specific conditions.

Current Stage
SQE Office 12 C

Step 6/13

Post approval, contracting and financing

A lead contractor(s) is appointed to build the project and all pre-construction approvals and consents are finalised. During this phase the lead contractor(s) is provided with a list of local businesses that have registered their interest and capabilities through the project website.

Current Stage
SQE Office 3 C

Step 7/13

Procurement

During this phase our lead contractor(s) seek tenders and engage contractors and suppliers to undertake the scope of the works. Orders are then placed for major components such as the wind turbines.

Current Stage
DSCN6131

Step 8/13

Early works and design

Initial site activities commence, such as minor clearing and provision of access roads along with establishing a site construction compound. Off-site detailed design works commences in parallel.

Current Stage
4 170607 WTG wide

Step 9/13

Major civil works

During this phase of the construction the bulk of the civil works takes place. This includes the construction of new internal access roads, excavation and construction of the turbine foundations, installation of the internal electrical reticulation system, construction of the high voltage substation and main transmission line network.

Current Stage
01 Final foundation pour 2

Step 10/13

Wind turbine erection

This is where the visual aspect of the wind farm starts to emerge, with large cranes lifting the tower sections, nacelle, hub and blades into place.

Current Stage
CWP Crudine Ridge Wind Farm JOW 201125 0131

Step 11/13

Commissioning

In order to export power to the grid, each turbine is required to undergo several performance tests. It is during this stage that you will start to see turbines spinning and ultimately the whole of the wind farm complete.

Current Stage
SWF 03 Sapphire Wind Farm landscape 230724 12

Step 12/13

Operations

The project is operating in accordance with relevant approval conditions and management plans. Compliance with conditions of approval and management plans is monitored as required throughout the life of the project.

Current Stage
CWP Sapphire Wind Farm JOW 201111 7104

Step 13/13

Decommissioning

The design life of the wind turbines will be at least 30 years. At the end of their useful life, the wind turbines and electrical equipment will be either replaced and the wind farm repowered, or the project will be decommissioned, and the site returned to its original use at the expense of the project.

Current Stage
20231113 i Phone Bango Wind Farm 72

Squadron Energy in the community

Murra Warra II Wind Farm is committed to supporting the local community through its Sustainable Community Grant Fund, supporting local community projects. The MWWF Sustainable Community Grant Fund is made up of the Murra Warra Wind Farm Stage 1 and Stage 2 projects, with a total of $99,000 committed to the Fund each year.

The Fund promotes social and environmental sustainability initiatives through supporting educational, environmental, and community-based projects that are consistent with the principles of sustainable development.

Brendan Ab3  

Community

IMG 4573 Niel DC  

Western Victoria Renewable Energy Zone

The Victorian Government has identified six areas within the State as Renewable Energy Zones. Murra Warra II Wind Farm is located in the Western Victoria REZ.

Renewable Energy Zones involve the coordinated development of new grid infrastructure in energy rich areas, to connect multiple renewable energy generators (such as wind farms) in the same location.

20231113 DJI Bango Wind Farm 6  

About Squadron Energy

Squadron Energy is Australia’s leading renewable energy company that develops, operates and owns renewable energy assets in Australia. We are 100% Australian owned and have 1.1 gigawatts (GW) of renewable energy in operation and 900MW under construction. We are committed to delivering a 14GW development pipeline by 2030, powering the equivalent of six million homes.

Contact

Mailing Address

Murra Warra II Wind Farm
Suite 6.01, Level 6
165 Walker Street
North Sydney
NSW 2060

Newsletter

Receive the latest Murra Warra II Wind Farm project updates straight to your inbox